Josef’s Work Schedule for the new house

August 1905 – hewed timbers for house, posts under house, sills and joist, divided space, boarded walls.September 1905 – outside walls, shingles, upstairs windows
October 1905 – painted roof, worked on staircase
November 1905 – planed floor
December 1905 – chimney, began cupboards